Short Description
The Time Correctionmodule enables a user to calculate periodic pro-rate voyage days (or proration) for a selected period per business unit/s. The Time Correction module is part of the Period-End-Closing process and must be run (to update/refresh data) prior to closing a period.
...
| Anchor | ||||
|---|---|---|---|---|
|
...
Go to
Modules > Accounting > Time Correction.The Time Correction window opens.
Note: Any previous proration data displays in the main panel of the module. If no previous proration have been run - the view will be empty.
Example:Click Run Time Correction... A dialog box opens.
Example:- Fill in the fields as follows:
- Select the month (from the drop-down menu) and the year to run time correction from under From Month/Year.
- Select the month (from the drop-down menu) and the year to run time correction to under To Month/Year.
- Click the applicable business unit/s under Business Unit.
- Enter either
- the vessel code to update proration data for a single vessel (if applicable) under Vessel Class
- or click the Triple Dot Selector next to the field. A pop-up with a list of input values opens. Select field and click OK.
Example:
- Click Generate. A pop-up opens requesting confirmation start time correction. The process may take a while.
- Click OK. The pop-up will close and the time correction process commence.
- Once the time correction is complete, a pop-up opens with advising this.
- Click OK. The pop-up will close and the updated/refreshed time correction (or proration) data for each voyage of the selected business unit/s for the specified period appear as rows.
Example:
8. Once proration is complete: to continue accounting period closing - return to the Period-End-Closing Process page.
...
| Anchor | ||||
|---|---|---|---|---|
|
...
...
- Go to
Modules > Accounting > Time Correction.The Time Correction window opens. - Verification consists of two steps:
- Ensure that the breakdown days of each row matches its total number of days:
- Filter the updated proration list to display the records for the relevant period only.
- Click the magnifying glass icon at the top-right corner.
- A row displays above the columns.
- Type
- relevant year in the field above the Year column
- and relevant month in the field above the Month column.
Note: Enter month as m or mm, for example: if running for March, type either '03' or '3' to show only the records for this period.
Example:
- Press Enter.
- Review and verify the final resulting list of data, especially the Total Days column and the five columns detailing the breakdown of days: Onhire Days, RBSD Days (Repair, Breakdown, Supply, Delay), Dry Dock Days, Ballast to Dry Dock Days and Idle Days.
- Ensure that the total number of days/month for a vessel matches the number of days/month:
- Follow the step-by-step instructions of Steps 1-2v above.
- Once the period to be verified display, click the calculation icon at the top-right corner.
- At the bottom of the screen a status bar indicates the sums of each column. Check that the total number of days matches the number days of the prorated month.
Example:
Proration run form January 2012.
- Ensure that the breakdown days of each row matches its total number of days:
3. Once the verification is complete: to continue accounting period closing - return to the Period-End-Closing Process page.
...
| Expand | ||
|---|---|---|
| ||
|