Inserting a Voyage Between Frozen Voyages?
Inserting a Voyage Between Frozen Voyages?
Question
Is it possible to set a voyage's start date and numbering when freezing it, i.e. schedule it to be performed between two already exisiting voyages?
Answer
Yes, this is possible. By dafualt Dataloy VMS schedules a newly frozen voyage after the one last entered. To avoid this follow the below steps. The voyages will automatically re-order.
To change voyage sequence/s:
- Freeze the voyage.
Note: Here: If there are voyages with sequence numbers 1 and 2, this will be nr. 3. - Go to Modules > Booking and Operations > Booking and Operations. The Booking and Operations window will open.
- Click applicable vessel in the By Vessel Tab (left-hand field) - it will highlight - it's details display will display in the right-hand and lower fields.
In the right-hand Voyage List tab all the vessel's voyages are listed - the most recent by default at the top.
In the Voyage List field click the voyage to change the start date for - it will highlight and its details display.
- Check Lock Start Date for the voyage.
- In the voyage's Start Date column field enter a date between the start and end dates of the voyages the voyage is to be inserted between.
- Uncheck Lock Start Date.
- Change the voyage numbers.
Note: Changing voyage numbers requires a small "workaround", for example: if the list is 1, 2, 3 - change 3 to 99, 2 to 3 and then 99 to 2. IMPORTANT: If invoices have already been posted or other accounting transactions made against the voyage either keep the voyage number unchanged or request your company's IT department to change it in applicable accounting system.
Related articles
, multiple selections available,
Related content
Change Voyage Sequence?
Change Voyage Sequence?
More like this
Can Voyage Numbering be Customised?
Can Voyage Numbering be Customised?
More like this
Add Time Charter (TC) In Contract to Frozen Voyage and Generate Hire Statement
Add Time Charter (TC) In Contract to Frozen Voyage and Generate Hire Statement
More like this
Create-Unallocated-Voyages Process
Create-Unallocated-Voyages Process
More like this
Voyage Schedule not Updated After Adding New Cargo and Ports
Voyage Schedule not Updated After Adding New Cargo and Ports
More like this
How to Create a Voyage Which is Only Offhire?
How to Create a Voyage Which is Only Offhire?
More like this